Links
ICBS
Safety


Interoperable Communication-Based Signaling refers to a communications-based train control systems developed around well-defined and accepted signaling principles.  System Architecture and Interface Specifications are being finalized through AREMA Committee 37 (Signal Systems).  The Federal Railroad Administration (FRA) has awarded a grant to demonstrate the system architecture and the interoperability interfaces as defined in the draft AREMA Manual Parts.  This is being coordinated through the Railroad Research Foundation.

The following presentatin and paper were done for the AAR's Railway Electronics Steering Committee (RESC) on October 1, 2008.  (See the 2008 AREMA S&C Conference paper below for more detailed information).


The following presentation and paper were done for the 2008 AREMA Communication and Signal Technical Conference held September 23, 2008.



The following article regarding ICBS was published in the May 2008 issue of Railway Age.


The following presentation was done for the Institution of Railway Signal Engineers (IRSE) Annual General Meeting of the North American Section.  It provides a project update as well as some thoughts on how Part 236 subpart H might be applied.


The following paper (and presentation) provide information regarding the background, architecture, interfaces and benefits of the communication-based signaling approach.

May 2007 AREMA C&S Technical Conference Paper
May 2007 AREMA C&S Technical Conference Presentation

The following articles have been published recently discussing ICBS, among other systems.  See Links page for direct links to magazine websites.



The following presentation was given to the Midwest Regional Rail Initiative (MWRRI)  PTC Symposium on December 12, 2007

 Midwest Regional Rail PTC Symposium Presentation

One of the presentations at the MWRRI meeting discussed cost-benefit analysis of PTC systems.  The full report is linked below, noting the substantial concerns raised by the railroads about the analysis.  The cover letter from the acting FRA administrator identifies some of the concerns.
PTC Cost-Benefit Report


August 7, 2008 Update

The CAD simulator, the Critical Link simulators / test drivers, and both the Safetran Wayside Appliance and the Safetran Signaling Logic Processor subsystem have been integrated and the system is operational.  We have moved multiple trains through the territory (both following and opposing moves) under dispatch control.  Some issues (minor) were identified and will be addressed in future revisions.  Alstom, GETS and US&S are continuing work on their subsystems and they will be integrated into the overall system over the next couple months.

CAD Screens   Overall and Detail Screens from CAD Layout

Safetran WA and SLP subsystems   Safetran WA and SLP subsystems


OnBoard Logic Processor Simulator Screen    OnBoard Logic Processor Display Screen

Test Simulators  Test Environment Running Simulators for entire territory, including integrating
                                                                                    Safetran subsytems.

Brain Trust   Part of the Brain Trust


July 7, 2008 Update

The communications router for the test environment has been completed and distributed to participating suppliers.  Additional test drivers and/or simulators for all the subsystem components have been completed and will be distributed shortly.  These will allow suppliers to thoroughly test their subsystems prior to final integration and demonstration.  As subsystems are being developed, improvements and changes are being incoroporated into a modified set of AREMA Manual Parts which will be presented to the committtee at the conclusion of this project.


May 20, 2008 Update

Work is continuing on development of the components to be tested.  Critical Link has completed the core communications simulator and is sending / receiving messages.


March 28, 2008 Update

The AREMA Manual parts have been approved by AREMA Committee 37 and will be published in the 2009 AREMA C&S Manual (available in Fall 2008).  As noted in the introduction to the Manual Parts, they will continue to be enhanced based on lessons learned through the ICBS project.

A Project meeting was held with all participants in conjunction with the AREMA C37 meetings in early March.  Each supplier presented their plans for how they will proceed on the project.  (Alstom has now formally committed to supporting the project and was a full participant in the meeting).    The test territory and supporting infrastructure database has been completed.  Each supplier will be responsible for a section of territory consisting of 2 tracks (and one additional siding), with a single crossover, a universal crossover and a scissors crossover in the territory.  OnBoard equipment will be supplied by Alstom, GETS, and Union Switch and Signal.  All 4 suppliers, including Safetran Systems,  will provide Signaling Logic processors and Wayside Appliance.

Critical Link is proceeding with the high level designs and test environment.

A project update will be published in the May issue of Railway Age.

A presentation on ICBS will be done for the Institution of Railway Signal Engineers North American Section Annual General Meeting on May 20, 2008 (immediately preceding the RSSI Annual Exhibition in Grapevine, Texas)

A presentation on ICBS will be done for the AREMA Annual Technical Conference (currently scheduled for 2:30 PM on Sept 23 during the C&S session) on September 21-24 in Salt Lake City.





January 16, 2008 Update

Subcontracts with each of the participants are mostly in place.  A kickoff meeting was held in December and additional meetings on the test environment were held in early January.  Work is proceeding on the simulators and overall test environment.  It was decided to use the territory described in the example in MP 23.5.1 for each of the suppliers equipment.  

Alstom has indicated that they would like to participate in the testing along with the other suppliers and discussions are proceeding.   This will be in addition to the efforts covered by the cooperative agreement.

The Manual Parts were balloted and comments will be addressed at the next meeting of Committee 37 (tentatively in early March).

November 22, 2007 Update

A Cooperative Agreement ( DTFR53-07-H-00005) has been finalized between the FRA Office of Research and Development and the Railroad Research Foundation (RRF) to allow for system demonstration through a lab test; and to verify the interoperability specifications provided in the AREMA Manual Parts.    Project Management will be provided by me (Bill Petit) through a subcontract with the RRF.  Simulators and Test Environment will be provided by Critical Link.  GETS, SSC and US&S will each provide assistance with the simulators and will modify their existing signal equipment (e.g. interlocking controllers, wayside object controllers, onboard cab signal equipment) to comply with the CBS interface specifications.  Testing will demonstrate train movements through a typical territory using combinations of the various suppliers equipment.  A Kickoff meeting is currently scheduled for December 4th at the Critical Link facilities.

The draft Manual Parts were reviewed at the Fall AREMA Committee 37 meeting and will be submitted for ballot to be included in the next edition of the AREMA Manual on Communications and Signaling.  Assuming approval, they will be published in a new Section 23 of the manual.